Thursday, June 23, 2011

Lakeway Regional Medical Center

Sam's hospital is coming along. Here are the latest pics and some info. on the progress. Way to go Sam and Amy!



Highlights of the construction process are:

• All structural concrete is complete

• Propane pad and curbs are complete for our 20,000 gallon tank and the 2,000 gallon tank are set and scheduled for repainting.

• Stone installation is complete at the east elevation and 80% complete at the south elevation

• Helipad construction is 90% complete

• Main electrical switchgear has been delivered and is being installed

• All air chillers and heat exchanges are installed in lower level 3

• Oxygen and propane supply piping is complete

• Kitchen hood and freezers are installed

• Daily main power in site is approximately 305

We anticipate having the hospital watertight in the next 45 days.