Highlights of the construction process are:
• All structural concrete is complete
• Propane pad and curbs are complete for our 20,000 gallon tank and the 2,000 gallon tank are set and scheduled for repainting.
• Stone installation is complete at the east elevation and 80% complete at the south elevation
• Helipad construction is 90% complete
• Main electrical switchgear has been delivered and is being installed
• All air chillers and heat exchanges are installed in lower level 3
• Oxygen and propane supply piping is complete
• Kitchen hood and freezers are installed
• Daily main power in site is approximately 305
We anticipate having the hospital watertight in the next 45 days.